Humber Gateway A is an operational 219 MW offshore wind farm in DECC (S36), generating since 30 May 2015. Planning permission was granted on 9 February 2011, 34 months after submission. Operator of record: E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix..

219 MW
Capacity
as recorded in REPD
Operational
Status
since 30 May 2015
Wind Offshore
Technology
E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix.
DECC (S36)
Authority
England

Planning and build timeline

Application submitted1 April 2008
Permission granted9 February 2011
34 months after submission
Operational30 May 2015
52 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Humber Gateway A’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

How big is Humber Gateway A?

Humber Gateway A has a recorded installed capacity of 219 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Humber Gateway A?

REPD records the operator as E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix.. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Humber Gateway A approved and built?

The application was submitted on 1 April 2008. Permission was granted on 9 February 2011, 34 months later. The site became operational on 30 May 2015, 52 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2544.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode