Renewable sitesHornsea 1 - Heron & Njord

Hornsea 1 - Heron & Njord

Hornsea 1 - Heron & Njord is an operational 1.22 GW offshore wind farm in England, generating since 1 December 2019. Planning permission was granted on 10 December 2014, 16 months after submission. Operator of record: Orsted (formerly Dong Energy).

1.22 GW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2019
Wind Offshore
Technology
Orsted (formerly Dong Energy)
National
Authority
England

Planning and build timeline

Application submitted30 July 2013
Permission granted10 December 2014
16 months after submission
Operational1 December 2019
60 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hornsea 1 - Heron & Njord’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

How big is Hornsea 1 - Heron & Njord?

Hornsea 1 - Heron & Njord has a recorded installed capacity of 1.22 GW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hornsea 1 - Heron & Njord?

REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hornsea 1 - Heron & Njord approved and built?

The application was submitted on 30 July 2013. Permission was granted on 10 December 2014, 16 months later. The site became operational on 1 December 2019, 60 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2525.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode