Renewable sites › Hendy Wind Farm
Hendy Wind Farm
Hendy Wind Farm is under construction in Powys with a recorded capacity of 14.4 MW.
Planning and build timeline
| Application submitted | 2014-07-14 |
| Permission granted | 2018-10-25 51 months after submission |
| Operational | not recorded |
Powys’s record on onshore wind
Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys →
How big is Hendy Wind Farm?
Hendy Wind Farm has a recorded installed capacity of 14.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hendy Wind Farm?
REPD records the operator as Njord Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hendy Wind Farm approved and built?
The application was submitted on 2014-07-14. Permission was granted on 2018-10-25, 51 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4377.