Renewable sites › Grudie
Grudie
Grudie is operational in Highland with a recorded capacity of 2 MW, and has been generating since 2017-09-29.
Planning and build timeline
| Application submitted | 2013-06-20 |
| Permission granted | 2014-09-17 15 months after submission |
| Operational | 2017-09-29 36 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Garbhaig Hydro Scheme Small Hydro · Operational | 2 | 7.3 km |
How big is Grudie?
Grudie has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Grudie?
REPD records the operator as RWE Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Grudie approved and built?
The application was submitted on 2013-06-20. Permission was granted on 2014-09-17, 15 months later. The site became operational on 2017-09-29, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 493.
Novarly Parcel · official public data, read properly · parcel.novarly.com