Ghuilbinn Hydro Scheme

Ghuilbinn Hydro Scheme is operational in Highland with a recorded capacity of 2 MW, and has been generating since 2017-10-01.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-10-01
Small Hydro
Technology
Corrour Property Company
Highland
Authority
Scotland

Planning and build timeline

Application submitted2014-04-25
Permission granted2014-09-09
5 months after submission
Operational2017-10-01
37 months after consent

Other built sites within 15 km

SiteMWDistance
River Pattack
Small Hydro · Operational
212.1 km
Loch Ericht
Small Hydro · Operational
2.214.4 km

How big is Ghuilbinn Hydro Scheme?

Ghuilbinn Hydro Scheme has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ghuilbinn Hydro Scheme?

REPD records the operator as Corrour Property Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ghuilbinn Hydro Scheme approved and built?

The application was submitted on 2014-04-25. Permission was granted on 2014-09-09, 5 months later. The site became operational on 2017-10-01, 37 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 495.