Gameslack Farm

Gameslack Farm is a 17.5 MW biomass plant under construction in East Riding of Yorkshire. Planning permission was granted on 26 October 2015, 3 months after submission. Operator of record: East Yorkshire Power.

17.5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Biomass (dedicated)
Technology
East Yorkshire Power
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted27 July 2015
Permission granted26 October 2015
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in East Riding of Yorkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Gameslack Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
28.1 km

How big is Gameslack Farm?

Gameslack Farm has a recorded installed capacity of 17.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gameslack Farm?

REPD records the operator as East Yorkshire Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gameslack Farm approved and built?

The application was submitted on 27 July 2015. Permission was granted on 26 October 2015, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5674.