Galloper Wind Farm
Galloper Wind Farm is operational in England with a recorded capacity of 353 MW, and has been generating since 2018-03-30.
Planning and build timeline
| Application submitted | 2011-11-21 |
| Permission granted | 2013-05-24 18 months after submission |
| Operational | 2018-03-30 58 months after consent |
What this site sits on
- Special Area of Conservation — Southern North Sea
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Greater Gabbard Wind Farm Wind Offshore · Operational | 504 | 8.7 km |
How big is Galloper Wind Farm?
Galloper Wind Farm has a recorded installed capacity of 353 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Galloper Wind Farm?
REPD records the operator as RWE Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Galloper Wind Farm approved and built?
The application was submitted on 2011-11-21. Permission was granted on 2013-05-24, 18 months later. The site became operational on 2018-03-30, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2526.