Novarly ParcelRenewable sites

Renewable sitesDogger Bank A & B (was Creyke Beck A & B)

Dogger Bank A & B (was Creyke Beck A & B)

Dogger Bank A & B (was Creyke Beck A & B) is a 2.40 GW offshore wind farm under construction in England. Planning permission was granted on 17 February 2015, 18 months after submission. Operator of record: SSE/Equinor (formerly Statoil, formerly Forewind).

2.40 GW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Offshore
Technology
SSE/Equinor (formerly Statoil, formerly Forewind)
National
Authority
England

Planning and build timeline

Application submitted29 August 2013
Permission granted17 February 2015
18 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dogger Bank A & B (was Creyke Beck A & B)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Dogger Bank A & B (was Creyke Beck A & B)?

Dogger Bank A & B (was Creyke Beck A & B) has a recorded installed capacity of 2.40 GW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dogger Bank A & B (was Creyke Beck A & B)?

REPD records the operator as SSE/Equinor (formerly Statoil, formerly Forewind). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dogger Bank A & B (was Creyke Beck A & B) approved and built?

The application was submitted on 29 August 2013. Permission was granted on 17 February 2015, 18 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2541.

Novarly Parcel · official public data, read properly · parcel.novarly.com