Den Brook
Den Brook is an operational 18 MW onshore wind farm in West Devon, generating since 17 November 2016. Planning permission was granted on 21 March 2007, 16 months after submission. Operator of record: Aviva.
Planning and build timeline
| Application submitted | 10 November 2005 |
| Permission granted | 21 March 2007 16 months after submission |
| Operational | 17 November 2016 116 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in West Devon: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Den Brook’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 12 | 2.9 km |
Solar Photovoltaics · Operational | 1.4 | 8.1 km |
Solar Photovoltaics · Operational | 2.8 | 10.1 km |
Solar Photovoltaics · Operational | 1.1 | 12 km |
How big is Den Brook?
Den Brook has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Den Brook?
REPD records the operator as Aviva. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Den Brook approved and built?
The application was submitted on 10 November 2005. Permission was granted on 21 March 2007, 16 months later. The site became operational on 17 November 2016, 116 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4266.