Renewable sitesCraigahulliar Landfill Gas

Craigahulliar Landfill Gas

Craigahulliar Landfill Gas is an operational 1 MW landfill gas site in Causeway Coast and Glens, generating since 12 December 2012. Planning permission was granted on 19 September 2011, 13 months after submission. Operator of record: B9 Organic Energy and Craigahulliar Energy.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 12 December 2012
Landfill Gas
Technology
B9 Organic Energy and Craigahulliar Energy
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted2 September 2010
Permission granted19 September 2011
13 months after submission
Operational12 December 2012
15 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Causeway Coast and Glens: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Craigahulliar Landfill Gas’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Craigahulliar Landfill Gas?

Craigahulliar Landfill Gas has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Craigahulliar Landfill Gas?

REPD records the operator as B9 Organic Energy and Craigahulliar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Craigahulliar Landfill Gas approved and built?

The application was submitted on 2 September 2010. Permission was granted on 19 September 2011, 13 months later. The site became operational on 12 December 2012, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 773.