Craigahulliar Landfill Gas
Craigahulliar Landfill Gas is operational in Causeway Coast and Glens with a recorded capacity of 1 MW, and has been generating since 2012-12-12.
Planning and build timeline
| Application submitted | 2010-09-02 |
| Permission granted | 2011-09-19 13 months after submission |
| Operational | 2012-12-12 15 months after consent |
How big is Craigahulliar Landfill Gas?
Craigahulliar Landfill Gas has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Craigahulliar Landfill Gas?
REPD records the operator as B9 Organic Energy and Craigahulliar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Craigahulliar Landfill Gas approved and built?
The application was submitted on 2010-09-02. Permission was granted on 2011-09-19, 13 months later. The site became operational on 2012-12-12, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 773.