Novarly ParcelRenewable sites

Renewable sitesBeatrice Demonstrator

Beatrice Demonstrator

Beatrice Demonstrator is operational in Scotland with a recorded capacity of 10 MW, and has been generating since 2007-07-17.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2007-07-17
Wind Offshore
Technology
Talisman Energy
National
Authority
Scotland

Planning and build timeline

Application submitted2006-01-23
Permission granted2006-06-15
5 months after submission
Operational2007-07-17
13 months after consent

How big is Beatrice Demonstrator?

Beatrice Demonstrator has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beatrice Demonstrator?

REPD records the operator as Talisman Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beatrice Demonstrator approved and built?

The application was submitted on 2006-01-23. Permission was granted on 2006-06-15, 5 months later. The site became operational on 2007-07-17, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2485.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council