Novarly ParcelRenewable sites

Renewable sitesAllt na Moine

Allt na Moine

Allt na Moine is under construction in Highland with a recorded capacity of 2 MW.

2 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Small Hydro
Technology
RWE Npower Renewables / Innogy
Highland
Authority
Scotland

Planning and build timeline

Application submitted2014-01-16
Permission granted2014-07-28
6 months after submission
Operationalnot recorded

How big is Allt na Moine?

Allt na Moine has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Allt na Moine?

REPD records the operator as RWE Npower Renewables / Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Allt na Moine approved and built?

The application was submitted on 2014-01-16. Permission was granted on 2014-07-28, 6 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 489.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council