Novarly ParcelRenewable planning

Renewable planning SolarSt Albans

Solar planning in St Albans

St Albans has decided 10 solar farms and approved 100% of them, taking a median of 1.6 months to decide. Consented capacity: 3 MW. 5 applications still awaiting a decision.

100%
Approved
10 granted · 0 refused
1.6 mo
Median decision
UK 2.3 mo
3 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How St Albans compares

Against the 298 UK authorities with 5+ solar decisions, St Albans sits in the 77th percentile for approval rate (7 points above the England average) and the 92nd percentile for speed.

Decisions by year

35Approved — 4 (2023)423Approved — 3 (2024)324Approved — 1 (2025)125Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (16)

SchemeMWStatusDecided
Sainsburys Supermarkets - Solar Panels
Sainsbury's Supermarkets Limited · 5/2026/0343
0.6Application Submitted2026-02-20
The Albert Bygrave Retail Park, North Orbital Road - Solar Panels
ABRP Uk Limited · 5/2025/2095 · 1.8 mo to decide
Awaiting Construction2026-01-21
St Albans School, Abbey Gateway - Solar Panels
St Albans School · 1.6 mo to decide
0.19Awaiting Construction2025-08-20
Beechtree Junction, Potters Crouch - Solar PV Panels
Exagen Development Limited · 5/2025/1132
49.9Application Submitted2025-07-04
Hatfield Road - Solar Panels
Gondola Pro · 5/2024/1458 · 1.6 mo to decide
0.29Awaiting Construction2024-10-10
The Range, Graham Close - Roof Mounted Solar Panels
Natwest Trustee & Depository Services Limited · 5/2024/0795 · 1.8 mo to decide
0.47Awaiting Construction2024-07-02
Spire Harpenden Hospital - Solar Panels
Spire Healthcare · 5/2024/0403 · 1.8 mo to decide
0.26Awaiting Construction2024-06-04
Sandringham school, The Ridgeway - Solar Panels
Earthpoints Limited · 5/2023/2209 · 1.6 mo to decide
0.16Awaiting Construction2023-12-19
Verulam School - Solar Panels
Earthpoints Limited · 5/2023/2211 · 1.4 mo to decide
0.17Awaiting Construction2023-12-14
St Albans Retail Park, Griffiths Way - Solar Panels
Natwest Trustee & Depository Services Limited · 5/2023/1803 · 1.3 mo to decide
0.79Awaiting Construction2023-10-04
Verulam School, Brampton Road - Solar Panels
Earthpoints Limited · 5/2023/1723
0.16Revised2023-08-11
Sandringham School, The Ridgeway - Solar Panels
Earthpoints Limited · 5/2023/1724
0.48Revised2023-08-11
The Maltings Shopping Centre - Solar Array
St Albans (Maltings 4) Limited · 5/2023/1283 · 1.5 mo to decide
0.33Awaiting Construction2023-08-04
Westminster Lodge Leisure Centre - Solar Panels
St Albans City & District Council · 5/2022/0666
0.18Application Submitted2022-03-15
Samuel Ryder Academy - Solar panels
Scholars Education Trust · 5/2021/0521
0.2Application Withdrawn2021-04-13
Aylett Nurseries - Solar Panels
Aylett Nurseries
Operational

Does St Albans approve solar farms?

Yes — of the 10 solar farms St Albans has decided, 100% were approved (10 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in St Albans?

The median time from application to decision is 1.6 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has St Albans consented?

3 MW has been consented across 10 approved schemes. A further 5 applications awaits a decision.

Other technologies in St Albans

Battery storage in St AlbansOnshore wind in St Albans

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.