Solar planning in South Tyneside

South Tyneside has decided 8 solar farms and approved 100% of them, taking a median of 1.4 months to decide. Consented capacity: 3 MW. 2 applications still awaiting a decision.

100%
Approved
8 granted · 0 refused
1.4 mo
Median decision
UK 2.3 mo
3 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How South Tyneside compares

Against the 298 UK authorities with 5+ solar decisions, South Tyneside sits in the 77th percentile for approval rate (7 points above the England average) and the 97th percentile for speed.

Decisions by year

35Approved — 1 (2023)123Approved — 1 (2024)124Approved — 5 (2025)525Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (10)

SchemeMWStatusDecided
Middlefields Depot, Middlefields Industrial Estate - Solar Panels
South Tyneside Metropolitan Borough Council · 260015 · 1.4 mo to decide
0.52Awaiting Construction2026-02-18
Dunes Amusement Arcade, Sea Road - Solar Panels
Dunes Adventure Island And Bowling Alley · 260063
0.15Application Submitted2026-02-11
Hebburn Lakes Primary School, Campbell Park Road - Solar PV Panels
Solar Options for Schools Limited · 250634 · 1.4 mo to decide
0.25Awaiting Construction2025-11-24
Mortimer community college, Reading Road - Solar Panels
Mortimer community college · 250636 · 1.3 mo to decide
0.32Awaiting Construction2025-11-24
Westoe Crown Primary School, Sea Winnings Way - Solar Panels
Westoe Crown Primary School · 250635 · 1.4 mo to decide
0.2Awaiting Construction2025-11-24
Clarendon, Windmill Way - Solar Panels
Choice Facilities Services · 250559 · 1.2 mo to decide
0.37Awaiting Construction2025-10-24
UTS Engineering, Pilgrimsway - Solar Panels
Utility Technology Services Limited · 250581 · 1.4 mo to decide
Awaiting Construction2025-10-22
Simonside Industrial Unit, Shaftesbury Avenue - Solar Panels
Kans and Kandy Property Limited · ST/0546/24/SPVPN · 0.9 mo to decide
0.36Awaiting Construction2024-10-08
E/o the Academy Of Light, Sunderland Road - Solar Farm
Sunderland AFC · ST/0357/24/FUL
40Application Submitted2024-07-02
Merchant House Warehouse, Tyne Dock - Solar Photovoltaics Equipment
Port Of Tyne · ST/0714/23/SPVPN · 1.7 mo to decide
0.69Awaiting Construction2023-11-17

Does South Tyneside approve solar farms?

Yes — of the 8 solar farms South Tyneside has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in South Tyneside?

The median time from application to decision is 1.4 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has South Tyneside consented?

3 MW has been consented across 8 approved schemes. A further 2 applications awaits a decision.

Other technologies in South Tyneside

Battery storage in South TynesideOnshore wind in South Tyneside

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.