Solar planning in Renfrewshire

Renfrewshire has decided 10 solar farms and approved 80% of them, taking a median of 5 months to decide. Consented capacity: 79 MW. 2 applications still awaiting a decision.

80%
Approved
8 granted · 2 refused
5 mo
Median decision
UK 2.3 mo
79 MW
Consented
10 MW refused
2
Appeals
0 allowed on appeal

How Renfrewshire compares

Against the 298 UK authorities with 5+ solar decisions, Renfrewshire sits in the 7th percentile for approval rate (13 points below the England average) and the 7th percentile for speed.

Decisions by year

35Refused — 2 (2016)216Approved — 3 (2023)323Approved — 3 (2024)324Approved — 2 (2025)225
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Lightyear Building, Marchburn Drive - Block A - Solar Panels
Sunbird Solar Solutions UK Limited · 25/0852/PP
0.41Application Submitted2026-01-29
Middleton Farm Cottage, Middleton Road - Solar Photovoltaic Array
Bluestone Energy Limited · 25/0232/PP · 5.1 mo to decide
40Awaiting Construction2025-09-03
Middleton Road, Linwood - Solar Photovoltaic Panels
Scottish Water Horizons · 24/0248/PP · 9.3 mo to decide
1.64Awaiting Construction2025-01-23
Locher Works, Kilbarchan Road - Solar Photovoltaic Array
Bluestone Energy · 24/0139/PP · 6 mo to decide
3Awaiting Construction2024-09-05
Bray Controls UK, Fountain Crescent - Solar Panels
Bray Valve & Controls (UK) · 24/0389/PP
0.2Application Submitted2024-07-29
Decathlon, Old Govan Road - Solar Panels
Decathlon · 23/0727/PP · 3.5 mo to decide
0.2Awaiting Construction2024-03-29
Cpi Medicines Manufacturing Centre, Netherton Square - Solar Panels
CPI · 23/0257/PP · 6.9 mo to decide
0.2Awaiting Construction2024-01-30
Glasgow Airport Solar Farm
AGS Airports Limited · 22/0746/PP · 4.9 mo to decide
19.9Under Construction2023-04-06
Cartside Avenue, Inchinnan - Solar Panels
Thomas Johnstone Limited · 22/0638/PP · 3.8 mo to decide
0.2Awaiting Construction2023-02-09
East Fulwood Greenock Road - Solar Farm
Springfield Limited / Aggreko · 22/0582/PP · 5.2 mo to decide
14.3Awaiting Construction2023-01-24
Weels Farm Solar Array
Environmental Energy Investments · 15/0821/PP · 2.7 mo to decide
4.9Appeal Refused2016-02-03
West Mitchelton Farm Solar Array
Environmental Energy Investments · 15/0802/PP · 2.7 mo to decide
4.9Appeal Refused2016-02-03

Does Renfrewshire approve solar farms?

Yes — of the 10 solar farms Renfrewshire has decided, 80% were approved (8 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Renfrewshire?

The median time from application to decision is 5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Renfrewshire consented?

79 MW has been consented across 8 approved schemes, with 10 MW refused. A further 2 applications awaits a decision.

Other technologies in Renfrewshire

Battery storage in RenfrewshireOnshore wind in Renfrewshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.