Novarly ParcelRenewable planning

Renewable planning SolarOxford

Solar planning in Oxford

Oxford has decided 10 solar farms and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 4 MW. 2 applications still awaiting a decision.

100%
Approved
10 granted · 0 refused
1.8 mo
Median decision
UK 2.3 mo
4 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Oxford compares

Against the 298 UK authorities with 5+ solar decisions, Oxford sits in the 77th percentile for approval rate (7 points above the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 3 (2023)323Approved — 3 (2024)324Approved — 1 (2025)125Approved — 2 (2026)226
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Building One, Wyndyke Furlong - Solar Panels
Gigaclear Plc · P26/V0496/N8A
0.17Application Submitted2026-02-25
Oxford Biomedica, Alec Issigonis Way - Solar Panels
DTZ Investors UK · 25/03333/SP56 · 1.8 mo to decide
Awaiting Construction2026-02-10
Littlemore Mental Health Centre - Solar Panels
Avrenim Group · 25/03157/SP56 · 1.7 mo to decide
0.2Awaiting Construction2026-01-23
David Lloyd Leisure, John Smith Drive - Solar Panels
David Lloyd Leisure Limited · 25/01868/SP56 · 1.5 mo to decide
0.38Awaiting Construction2025-09-15
Oxford Brookes University Sports Hall, Cheney Lane - Solar pv panels
Oxford Brookes University · 24/01569/SP56 · 2.4 mo to decide
0.17Awaiting Construction2024-09-09
The Oxford Spires Academy, Glanville Road - Solar panels
Solar Options for Schools Limited · 24/02045/SP56
0.52Application Submitted2024-08-27
Oxford High School, Belbroughton Road - Solar Panels
The Girls Day School Trust · 24/00988/SP56 · 1.8 mo to decide
0.25Awaiting Construction2024-06-20
John Radcliffe Hospital, Headley Way - Solar Panels
Oxford University Hospitals NHS Foundation Trust · 24/00047/SP56 · 1.7 mo to decide
Awaiting Construction2024-02-29
Wolfson College - Solar Panels
Wolfson College · 22/00382/FUL · 18.3 mo to decide
Awaiting Construction2023-09-04
Clive Booth Hall, John Garne Way - Solar Panels
Oxford Brookes University · 22/03035/SP56 · 4.9 mo to decide
0.19Awaiting Construction2023-05-19
Riverside House, Osney Mead - Solar Panels
Rebellion Limited · 22/02727/SP56 · 1.8 mo to decide
0.21Awaiting Construction2023-01-10
BMW UK Manufacturing Ltd
Free Green Energy · 13/03312/PDC
3Operational

Does Oxford approve solar farms?

Yes — of the 10 solar farms Oxford has decided, 100% were approved (10 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Oxford?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Oxford consented?

4 MW has been consented across 10 approved schemes. A further 2 applications awaits a decision.

Other technologies in Oxford

Battery storage in OxfordOnshore wind in Oxford

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.