Solar planning in Maidstone

Maidstone has decided 18 solar farms and approved 83% of them, taking a median of 1.9 months to decide. Consented capacity: 65 MW. 3 applications still awaiting a decision.

83%
Approved
15 granted · 3 refused
1.9 mo
Median decision
UK 2.3 mo
65 MW
Consented
14 MW refused
3
Appeals
1 allowed on appeal

How Maidstone compares

Against the 298 UK authorities with 5+ solar decisions, Maidstone sits in the 12th percentile for approval rate (10 points below the England average) and the 62nd percentile for speed.

Decisions by year

510Approved — 1 (2012)112Approved — 1 (2016)Refused — 1 (2016)216Approved — 2 (2022)222Approved — 2 (2023)Refused — 1 (2023)323Approved — 3 (2024)324Approved — 6 (2025)Refused — 1 (2025)725
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Coxheath County Primary School, Stockett Lane - Solar Panels
Solar Options for Schools Limited · 25/504269/PN14J · 1.8 mo to decide
0.17Awaiting Construction2025-12-11
Lockmeadow Centre, Barker Road - Solar Panels
Maidstone Borough Council · 25/502531/PN14J
0.39Application Withdrawn2025-10-20
Little Telpits Farm, Woodcock Lane - Solar Panels
Sarah Jane Grant · 25/502681/PN14J · 1.8 mo to decide
Awaiting Construction2025-08-27
Ewell Farm, Graveney Road -Solar Panels
Edward Vinson Limited · 25/501820/PN14J · 2.3 mo to decide
0.41Awaiting Construction2025-07-22
Cold Store, Rushett Lane - Solar Arrays
A Hinge & Sons Limited · 25/501794/PN14J · 2.2 mo to decide
0.15Awaiting Construction2025-07-08
Maidstone Borough Council Depot, Bircholt Road - Solar Panels
LASER Energy · 25/500512/PN14J · 3.3 mo to decide
0.18Awaiting Construction2025-05-24
Sutton Road, Langley - Solar Panels
Rumwood Green Farm Limited · 25/500401/PN14J · 1.8 mo to decide
0.83Awaiting Construction2025-04-04
Kent Medway Adolescent Hospital - Ground Mounted Solar Panels
Kent and Medway Adolescent Unit · 24/503785/FULL · 5.9 mo to decide
0.23Application Refused2025-03-12
Pattenden Lane - Solar PV Energy
ILOS Energy UK Limited · 24/505235/FULL
19Application Submitted2024-12-18
Mathurst Solar Farm, Goudhust Road - Solar PV Farm
Renewable Connections Developments Limited · 24/502235/FULL
18Application Submitted2024-07-11
Mid Kent College, Tonbridge Road - Air Source Heat Pumps & Solar Panels
Mid Kent College · 24/500613/FULL · 1.9 mo to decide
0.3Awaiting Construction2024-04-19
Ledian Farm, Upper Street - Solar Photovoltaic Panels
Senior Living (Ledian Farm) Limited · 24/500005/LAWPRO · 1.6 mo to decide
0.19Awaiting Construction2024-02-29
Eckley Farms, Marden - Solar Energy Farm
Statkraft Wind UK Limited · 22/501335/FULL · 20.2 mo to decide
49.9Awaiting Construction2024-02-05
East Hill Farm - Solar Panels
David Catt Limited · 23/502962/FULL · 1.8 mo to decide
Awaiting Construction2023-09-04
Berry Gardens, Redwall Lane - Solar Panels
Beba Energy Limited · 23/502844/FULL · 1.8 mo to decide
0.58Awaiting Construction2023-08-31
Mid Kent College, Tonbridge Road - Solar Panels
Mid Kent College · 23/503300/PN14J
0.35Application Submitted2023-07-14
Sainsburys Supermarkets, Station Road - Solar Panels
Sainsburys Supermarkets Limited · 23/502108/PN14J · 1.8 mo to decide
0.19Application Refused2023-06-27
St Leonards Road - Solar Panels
Fielder Filter Systems Limited · 22/502060/PNJ · 1.8 mo to decide
0.15Awaiting Construction2022-06-16
W M Morrisons Supermarkets - Solar panels
WM Morrisons Supermarkets Plc · 22/501010/PN14J · 1.8 mo to decide
0.36Awaiting Construction2022-04-22
Widehurst Farm
Wirsol (formerly Susenco) · 15/505971/FULL · 5.1 mo to decide
5Operational2016-03-03
Great Tong Solar Farm
Solar Securities · 15/505974/FULL · 6.2 mo to decide
4.9Appeal Withdrawn2016-02-29
Great Pagehurst Farm
Sunsave 22 (Pagehurst Farm) Limited · 13/1456 · 28.7 mo to decide
13.6Appeal Refused2016-02-11
East Lenham Solar Farm
Laurence Associates · 12/0013 · 9.4 mo to decide
6.6Operational2012-11-01

Does Maidstone approve solar farms?

Yes — of the 18 solar farms Maidstone has decided, 83% were approved (15 granted, 3 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Maidstone?

The median time from application to decision is 1.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Maidstone consented?

65 MW has been consented across 15 approved schemes, with 14 MW refused. A further 3 applications awaits a decision.

Other technologies in Maidstone

Battery storage in MaidstoneOnshore wind in Maidstone

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.