Solar planning in Hammersmith and Fulham

Hammersmith and Fulham has decided 5 solar farms and approved 100% of them, taking a median of 2.5 months to decide. Consented capacity: 1 MW. 3 applications still awaiting a decision.

100%
Approved
5 granted · 0 refused
2.5 mo
Median decision
UK 2.3 mo
1 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Hammersmith and Fulham compares

Against the 298 UK authorities with 5+ solar decisions, Hammersmith and Fulham sits in the 77th percentile for approval rate (7 points above the England average) and the 46th percentile for speed.

Decisions by year

35Approved — 2 (2023)223Approved — 2 (2024)224Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Westfield London Shopping Centre, Ariel Way - Solar Panels
Unibail-Rodamco-Westfield Group · 2025/03416/PDJ56
0.33Application Submitted2026-01-08
Hammersmith Hospital, Du Cane Road - Solar PV Panels
Imperial College Healthcare NHS Trust · 2025/00734/PDJ56 · 3.9 mo to decide
0.17Awaiting Construction2025-07-23
Harbour club, Watermeadow Lane - Solar Panels
Custom Solar Limited · 2023/03015/FUL
0.39Application Withdrawn2024-05-29
Fulham Pools, Lillie Road - Solar panels
Repowering London · 2024/00161/FUL · 2.5 mo to decide
0.29Awaiting Construction2024-04-09
Phoenix Fitness Centre, Phoenix Close - Solar Panels
Repowering London · 2024/00162/FUL · 1.8 mo to decide
0.18Awaiting Construction2024-03-21
Kern House, Scrubs Lane - Solar Panels
Big Yellow Group Plc · 23/0177/PRNOPDC · 1.8 mo to decide
Awaiting Construction2023-09-26
Harbour club, Watermeadow Lane - Solar Panels
Custom Solar Limited · 2023/01888/PDJ56
0.39Revised2023-09-18
Westfield London Shopping Centre, Ariel Way - Solar Panels
Unibail-Rodamco-Westfield · 2023/01724/PDJ56
1Application Submitted2023-06-28
The Queens Club, Palliser Road - Solar panels
The Queens Club · 2023/00499/FUL · 2.7 mo to decide
0.52Awaiting Construction2023-05-22

Does Hammersmith and Fulham approve solar farms?

Yes — of the 5 solar farms Hammersmith and Fulham has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Hammersmith and Fulham?

The median time from application to decision is 2.5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Hammersmith and Fulham consented?

1 MW has been consented across 5 approved schemes. A further 3 applications awaits a decision.

Other technologies in Hammersmith and Fulham

Battery storage in Hammersmith and FulhamOnshore wind in Hammersmith and Fulham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.