Solar planning in Gosport

Gosport has decided 5 solar farms and approved 100% of them, taking a median of 1.9 months to decide. Consented capacity: 2 MW.

100%
Approved
5 granted · 0 refused
1.9 mo
Median decision
UK 2.3 mo
2 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Gosport compares

Against the 298 UK authorities with 5+ solar decisions, Gosport sits in the 77th percentile for approval rate (7 points above the England average) and the 62nd percentile for speed.

Decisions by year

35Approved — 1 (2022)122Approved — 1 (2023)123Approved — 3 (2024)324
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Range Superstore, Gunners Way - Solar panels
Private Client · 24/00223/P14JPA · 1.9 mo to decide
0.43Awaiting Construction2024-08-30
Range Superstore, Gunners Way - Solar Panels
InRange Limited · 24/00223/P14JPA · 1.9 mo to decide
0.42Awaiting Construction2024-08-30
Immigration Removal Centre, Dolphin Way - Solar panels
Cushman and Wakefield · 24/00016/P14JPA · 1.8 mo to decide
0.23Awaiting Construction2024-03-21
Qinetiq Haslar, Haslar Road - Solar Panels
QinetiQ · 23/00051/FULL · 3.9 mo to decide
0.73Awaiting Construction2023-06-16
Walpole Road - Solar Panels
Morrisons · 22/00407/P14JPA · 2.4 mo to decide
0.16Awaiting Construction2022-12-15

Does Gosport approve solar farms?

Yes — of the 5 solar farms Gosport has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Gosport?

The median time from application to decision is 1.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Gosport consented?

2 MW has been consented across 5 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Gosport

Battery storage in GosportOnshore wind in Gosport

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.