Novarly ParcelRenewable planning

Renewable planning SolarErewash

Solar planning in Erewash

Erewash has decided 6 solar farms and approved 83% of them, taking a median of 2.7 months to decide. Consented capacity: 2 MW. 1 application still awaiting a decision.

83%
Approved
5 granted · 1 refused
2.7 mo
Median decision
UK 2.3 mo
2 MW
Consented
5 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Erewash compares

Against the 298 UK authorities with 5+ solar decisions, Erewash sits in the 12th percentile for approval rate (10 points below the England average) and the 42nd percentile for speed.

Decisions by year

35Refused — 1 (2015)115Approved — 3 (2022)322Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Boyah Grange Solar Farm, Potato Pit Lane - Solar Farm
ABEI Energy Group · 0825/0028
35.2Application Submitted2025-08-23
Donaldson Timber, Hallam Fields Road - Solar Panels
SNRG · 0125/0005 · 1.8 mo to decide
0.24Awaiting Construction2025-03-03
Brunswood Farm, Locko Road - Solar Panels
Private Developer · 0423/0015 · 9.2 mo to decide
0.2Awaiting Construction2024-01-11
Manners Avenue - Solar Panels
Creed Food Service Limited · 0122/0007 · 9 mo to decide
0.62Operational2022-10-06
Pinnacle Storage Park, Dale Abbey - Solar PV Panels
Hansteen Property Investments · 0322/0080 · 3.6 mo to decide
1Under Construction2022-07-07
Crompton Road - Solar Panels
St Johns Packaging Limited · 0322/0062 · 1.4 mo to decide
0.4Awaiting Construction2022-05-05
Ladywood Farm
Global Renewable Construction · 0915/0023 · 1.6 mo to decide
5Application Refused2015-10-28

Does Erewash approve solar farms?

Yes — of the 6 solar farms Erewash has decided, 83% were approved (5 granted, 1 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Erewash?

The median time from application to decision is 2.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Erewash consented?

2 MW has been consented across 5 approved schemes, with 5 MW refused. A further 1 application awaits a decision.

Other technologies in Erewash

Battery storage in ErewashOnshore wind in Erewash

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com