Renewable planning › Solar › Eastbourne
Solar planning in Eastbourne
Eastbourne has decided 6 solar farms and approved 100% of them, taking a median of 1.7 months to decide. Consented capacity: 22 MW. 3 applications still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Eastbourne compares
Against the 298 UK authorities with 5+ solar decisions, Eastbourne sits in the 77th percentile for approval rate (7 points above the England average) and the 87th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (9)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Whittle Drive - Solar Panels Gardners Books Limited · 250790 | 0.15 | Application Submitted | 2026-02-03 |
Suncoast Solar Farm Low Carbon Solar Park 20 Limited · 230800 · 14.7 mo to decide | 20 | Awaiting Construction | 2025-02-19 |
Broadwater Way - Solar Panels Sainsburys Supermarkets Limited · 240449 | 0.56 | Application Submitted | 2024-08-14 |
Bannatynes Gyms, Edward Road - Solar Photovoltaic Panels Ashcroft Electrical Services · 240317 · 1.7 mo to decide | 0.16 | Awaiting Construction | 2024-07-26 |
The David Lloyd Centre - Solar Panels David Lloyd Leisure Limited · 230398 | 0.38 | Application Submitted | 2023-07-04 |
Marshall Road - Solar Panels Zestec Asset Management · 230190 · 1.8 mo to decide | 0.2 | Awaiting Construction | 2023-05-03 |
Morrisons, Hargreaves Road - Solar Panels Gondola Pro / WM Morrisons · 220718� · 1.7 mo to decide | 0.29 | Awaiting Construction | 2022-10-28 |
Tesco Lottbridge Drove Tesco Stores · 190187 · 1.7 mo to decide | 0.2 | Operational | 2019-04-29 |
Eastbourne District General Hospital - Energy Management East Sussex Healthcare NHS Trust | 1.1 | Operational | — |
Does Eastbourne approve solar farms?
Yes — of the 6 solar farms Eastbourne has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a solar farm application take in Eastbourne?
The median time from application to decision is 1.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Eastbourne consented?
22 MW has been consented across 6 approved schemes. A further 3 applications awaits a decision.
Other technologies in Eastbourne
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.