Solar planning in East Staffordshire

East Staffordshire has decided 17 solar farms and approved 100% of them, taking a median of 2.7 months to decide. Consented capacity: 113 MW. 2 applications still awaiting a decision.

100%
Approved
17 granted · 0 refused
2.7 mo
Median decision
UK 2.3 mo
113 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How East Staffordshire compares

Against the 298 UK authorities with 5+ solar decisions, East Staffordshire sits in the 77th percentile for approval rate (7 points above the England average) and the 42nd percentile for speed.

Decisions by year

35Approved — 2 (2014)214Approved — 5 (2015)515Approved — 2 (2023)223Approved — 4 (2024)424Approved — 3 (2025)325Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (21)

SchemeMWStatusDecided
Queens Hospital Burton, Belvedere Road - Solar Panels
University Hospitals of Derby and Burton NHS Foundation · P/2026/00019 · 1.8 mo to decide
Awaiting Construction2026-02-04
Moreton Brook Farm, Lea Lane - Solar Farm
Aura Power Developments Limited · P/2024/0569/SOL · 8.6 mo to decide
49.9Awaiting Construction2025-07-25
Uttoxeter Leisure Centre, Oldfields Road - Solar PV Panels
East Staffordshire Borough Council · P/2025/00574 · 1.4 mo to decide
0.25Awaiting Construction2025-07-16
Stretton Business Park, Brunel Drive - Solar Panels
Project Better Energy · P/2025/00075 · 1.4 mo to decide
Awaiting Construction2025-03-28
Meadowside Leisure Centre, High Street - Solar Panels
East Staffordshire Borough Council · P/2024/01078
0.29Application Submitted2024-11-05
Port Way, Branston - Solar Panels
Leonardo Crawley Limited · P/2024/00450 · 2.8 mo to decide
0.65Awaiting Construction2024-08-02
Centrum East Retail Park - Solar Panels
Ashcroft Electrical Services Limited · P/2024/00577 · 1.7 mo to decide
0.2Awaiting Construction2024-08-01
Velis Kebab, Hawkins Lane - Photovoltaic Panels
Velis · P/2024/00233 · 1.2 mo to decide
0.17Awaiting Construction2024-04-15
Pirelli Limited, Derby Road - Solar Panels
Pirelli Limited · P/2024/00218 · 1 mo to decide
1.29Awaiting Construction2024-04-05
Hilton, St Georges Park - Solar Panels
Unknown · P/2023/01075 · 1.3 mo to decide
0.64Awaiting Construction2023-11-20
Rolleston Park Farm, Lodge Hill - Solar Farm
Push Generation & Supply Limited · P/2023/00296 · 7 mo to decide
12Awaiting Construction2023-11-03
Lanxess, Lichfield Road - Solar Panels
Beba Energy Limited · P/2023/00183
0.21Application Submitted2023-02-22
Rollston on Dove, Marston Lane
Lark Energy · P/2015/01064 · 3.1 mo to decide
5Abandoned2015-12-11
Woodhouse Fields Farm
Wirsol · P/2015/01032 · 3.4 mo to decide
5Operational2015-11-20
Land of Green Lane
TGC Renewables · P/2015/00791 · 2.7 mo to decide
5.8Operational2015-09-23
Solar farm at land at The Willows, Uttoxeter
TGC Renewables · P/2015/00434 · 3.3 mo to decide
6.4Operational2015-07-24
Morton House (Marchington)
Foresight Group (TGC Renewables) · P/2015/00405 · 2.8 mo to decide
6.2Operational2015-07-08
Blakenhall Park Solar Farm
Mercer Farming · P/2015/00401 · 2.2 mo to decide
1.8Operational2015-06-06
Marchington Solar Farm
Trina Solar · P/2014/00825 · 3.2 mo to decide
4.3Operational2014-10-15
Rolleston Park Farm
Push Energy · P/2014/00830 · 2.1 mo to decide
18.7Operational2014-09-10
Marchington Solar Park
Evans Group · P/2010/01499/JI · 30.8 mo to decide
4.2Abandoned2013-08-02

Does East Staffordshire approve solar farms?

Yes — of the 17 solar farms East Staffordshire has decided, 100% were approved (17 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in East Staffordshire?

The median time from application to decision is 2.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has East Staffordshire consented?

113 MW has been consented across 17 approved schemes. A further 2 applications awaits a decision.

Other technologies in East Staffordshire

Battery storage in East StaffordshireOnshore wind in East Staffordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com