Novarly ParcelRenewable planning

Renewable planning SolarDerby

Solar planning in Derby

Derby has decided 12 solar farms and approved 100% of them, taking a median of 1.7 months to decide. Consented capacity: 5 MW. 4 applications still awaiting a decision.

100%
Approved
12 granted · 0 refused
1.7 mo
Median decision
UK 2.3 mo
5 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Derby compares

Against the 298 UK authorities with 5+ solar decisions, Derby sits in the 77th percentile for approval rate (7 points above the England average) and the 87th percentile for speed.

Decisions by year

35Approved — 4 (2022)422Approved — 1 (2023)123Approved — 4 (2024)424Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (16)

SchemeMWStatusDecided
Landau Forte College, Fox Street - Solar Panels
eEnergy Group PLC · 26/00314/PNRPV
0.49Application Submitted2026-03-09
Florence Nightingale Community Hospital, London Road - Solar Panels
University Hospitals of Derby and Burton NHS Foundation Trust · 25/01831/PNRPV · 1.7 mo to decide
0.74Awaiting Construction2026-02-06
Lees Brook Community School, Morley Road - Solar Panels
eEnergy Group PLC · 26/00029/PNRPV
0.21Application Submitted2026-01-12
David Lloyd Health And Fitness Centre, Riverside Road - Solar Panels
David Lloyd Leisure Limited · 25/01133/PNRPV · 1.6 mo to decide
Awaiting Construction2025-08-29
Armadillo Self Storage, Foresters Park Centre - Solar Panels
Big Yellow Self Storage Limited · 25/00670/PNRPV · 1.7 mo to decide
0.23Awaiting Construction2025-06-13
Smartparc Food Hub, Evolution Way - Plot 8 Roof Mounted PV Solar Panels
SmartParc · 24/00568/FUL · 1.5 mo to decide
Awaiting Construction2024-06-04
Derbion Management Suite - Roof Mounted Solar panels
The Wilmslow (No 3) Limited Partner · 24/00064/PNRPV · 1.8 mo to decide
0.31Awaiting Construction2024-03-11
Firstsource, Riverside Road - Solar Panels
Justin Regional Reit · 24/00057/PNRPV · 1.7 mo to decide
0.77Awaiting Construction2024-03-08
Metal Improvement Company, Ascot Drive - Solar panels
Metal Improvement Inc · 23/01610/PNRPV · 1.7 mo to decide
0.16Awaiting Construction2024-01-24
Tenpin Bowling Derby, Foresters Park Centre - Solar Panels
Private Developer · 23/00988/PNRPV · 1.4 mo to decide
0.19Awaiting Construction2023-09-01
Dunelm Mill, Ascot Drive - Solar Panels
Dunelm Group Limited · 23/00512/PNRPV
0.16Application Submitted2023-04-11
St Christophers Way - Solar Panels
Private Developer · 22/00911/PNRPV · 1.7 mo to decide
0.35Awaiting Construction2022-07-22
Balfour Beatty Plant & Fleet Services, Raynesway - Solar Panels
Balfour Beatty · 22/01070/PNRPV
0.21Application Submitted2022-07-04
Chequers Road - Solar Panels
Inchcape Jaguar Derby · 22/00704/PNRPV · 1.7 mo to decide
0.25Awaiting Construction2022-06-24
Wheatcroft Way - Solar Panels
WM Morrisons Supermarkets Plc · 22/00199/PNRPV · 1.8 mo to decide
0.61Awaiting Construction2022-04-05
Victory Park Way - Solar Panels
Gardner Aerospace · 22/00242/FUL · 1.5 mo to decide
1.26Awaiting Construction2022-03-31

Does Derby approve solar farms?

Yes — of the 12 solar farms Derby has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Derby?

The median time from application to decision is 1.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Derby consented?

5 MW has been consented across 12 approved schemes. A further 4 applications awaits a decision.

Other technologies in Derby

Battery storage in DerbyOnshore wind in Derby

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com