Renewable planning › Solar › Cheltenham
Solar planning in Cheltenham
Cheltenham has decided 5 solar farms and approved 100% of them, taking a median of 1.3 months to decide. Consented capacity: 1 MW.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Cheltenham compares
Against the 298 UK authorities with 5+ solar decisions, Cheltenham sits in the 77th percentile for approval rate (7 points above the England average) and the 98th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (5)
| Scheme | MW | Status | Decided |
|---|---|---|---|
All Saints Academy, Blaisdon Way - Solar Panel All Saints Academy · 25/01602/PRIOR · 1.7 mo to decide | 0.18 | Awaiting Construction | 2025-11-25 |
Big Yellow Self Storage, Princess Elizabeth Way - Solar Panels Big Yellow Self Storage Limited · 24/01148/PRIOR · 1.5 mo to decide | 0.18 | Awaiting Construction | 2024-08-22 |
Ladies College Swimming Pool, Malvern Road - Solar Panels Ladies College Swimming Pool · 24/00844/PRIOR · 1.2 mo to decide | 0.16 | Awaiting Construction | 2024-06-21 |
St Pauls Medical Centre, Swindon Road - Solar Panels St Pauls Medical Centre · 24/00065/PRIOR · 1 mo to decide | 0.16 | Awaiting Construction | 2024-02-23 |
Sandfields Care Home, St Georges Road - Solar PV Panels Sandfields Care Home · 23/01479/PRIOR · 1.3 mo to decide | 0.15 | Awaiting Construction | 2023-10-05 |
Does Cheltenham approve solar farms?
Yes — of the 5 solar farms Cheltenham has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a solar farm application take in Cheltenham?
The median time from application to decision is 1.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Cheltenham consented?
1 MW has been consented across 5 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Cheltenham
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.