Novarly ParcelRenewable planning

Renewable planning SolarBroadland

Solar planning in Broadland

Broadland has decided 15 solar farms and approved 93% of them, taking a median of 3.3 months to decide. Consented capacity: 87 MW. 2 applications still awaiting a decision.

93%
Approved
14 granted · 1 refused
3.3 mo
Median decision
UK 2.3 mo
87 MW
Consented
25 MW refused
1
Appeals
1 allowed on appeal

How Broadland compares

Against the 298 UK authorities with 5+ solar decisions, Broadland sits in the 35th percentile for approval rate (level with the England average) and the 24th percentile for speed.

Decisions by year

35Approved — 1 (2012)112Approved — 2 (2014)214Approved — 1 (2015)115Approved — 2 (2021)221Approved — 2 (2022)222Approved — 3 (2023)323Approved — 1 (2024)124Approved — 2 (2025)Refused — 1 (2025)325
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (19)

SchemeMWStatusDecided
Warren Wood Energy Park - Solar Farm & Battery Energy Storage
Exagen Development Limited · 2025/1531 · 6.5 mo to decide
25Application Refused2025-12-05
Tesco Stores - Solar Panels
Solar Advanced Systems Limited · 2025/3062 · 1.3 mo to decide
0.33Awaiting Construction2025-11-17
Glebe Horsford - Solar Farm
Pathfinder Clean Energy UKDev Limited · 2023/2395 · 22.7 mo to decide
18Awaiting Construction2025-07-01
Hall Road, Alderford - Solar Panels
OPDE UK Limted · 2025/1969
28Application Submitted2025-07-01
D And F Mccarthy Limited, Memorial Way - Solar Panels
D And F Mccarthy Limited · 2024/0256 · 1.3 mo to decide
0.31Awaiting Construction2024-03-05
The Pump House - Ground Mounted Solar Photovoltaic Array
Private Developer · 2023/1237 · 3.3 mo to decide
0.27Awaiting Construction2023-08-11
Tc Fines, Norwich Road - Solar Array
T C Fines and Sons · 20230155 · 6.5 mo to decide
0.5Awaiting Construction2023-08-11
John Menzies Distribution, Memorial Way - Solar PV Panels
Menzies Distribution Limited · 20221941 · 1.8 mo to decide
0.19Awaiting Construction2023-01-30
Foxley Road, Themelthorpe - Solar Pv Panels
Noble Green Energy · 20220092 · 2.1 mo to decide
0.19Awaiting Construction2022-03-24
Docking Farm Solar
Metka EGN Projects Limited · 20211249 · 7.4 mo to decide
28Awaiting Construction2022-02-11
Wendover Road, Rackheath - Solar Panels
PSH Environmental · 20211973 · 1.7 mo to decide
0.28Awaiting Construction2021-12-17
Burgate Solar Farm
Pathfinder Clean Energy UK Dev Limited · 20202016 · 9.5 mo to decide
15Awaiting Construction2021-08-13
Oulton Street
Docking Farm Solar Limited · 20201776 · 7.1 mo to decide
17Revised2021-04-26
Oulton Airfield Solar Farm (Phase 1)
Solar Century/ Bluefield Solar · 20150952 · 3.3 mo to decide
5Operational2015-09-24
The Old Airfield
Lumicity · 20131702 · 3 mo to decide
5Operational2014-03-04
Salhouse Solar Farm
Island Green Power · 20131408 · 3.9 mo to decide
5Operational2014-02-05
Land off Belaugh Road
Trafford Estate Solar Park Ltd · 20121424
12Application Withdrawn2012-12-21
BELAUGH ROAD SOLAR FARM
Trafford Estate Solar Park Ltd · PF/12/1142
12Application Withdrawn2012-12-21
Woodforde Farm
Esconrg · 20121337 · 1.6 mo to decide
9Operational2012-11-06

Does Broadland approve solar farms?

Yes — of the 15 solar farms Broadland has decided, 93% were approved (14 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Broadland?

The median time from application to decision is 3.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Broadland consented?

87 MW has been consented across 14 approved schemes, with 25 MW refused. A further 2 applications awaits a decision.

Other technologies in Broadland

Battery storage in BroadlandOnshore wind in Broadland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.