South Norfolk has decided 6 onshore wind schemes and approved 0% of them, taking a median of 9.4 months to decide. 1 application still awaiting a decision.

0%
Approved
0 granted · 6 refused
9.4 mo
Median decision
UK 11.5 mo
0 MW
Consented
48 MW refused
4
Appeals
0 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How South Norfolk compares

Against the 75 UK authorities with 5+ onshore wind decisions, South Norfolk sits in the 0th percentile for approval rate (68 points below the England average) and the 78th percentile for speed.

Decisions by year

35Refused — 1 (2013)113Refused — 1 (2014)114
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Streetwood Wind Farm
TCI Renewables · 2013/0105 · 21.2 mo to decide
12Application Refused2014-10-27
Upper Vaunces Wind Farm
Upper Vaunces Wind Farm · 2013/0725 · 3.8 mo to decide
6Application Refused2013-08-21
Tivetshall St Mary Wind Farm
Enertrag UK · 2010/0861
9Application Withdrawn2013-03-04
Upper Vaunces Wind Farm
TCI Renewables · 2010/0383 · 9.4 mo to decide
7.5Revised2010-12-20
Pulham Airfield
SLP Energy
14Application Withdrawn2008-09-24
Hempnall
Enertrag UK · 07/2008/0917/F · 2.1 mo to decide
21Appeal Refused2008-08-05
Lotus Manufacturing
Ecotricity · 2007/1427 · 3.4 mo to decide
6Application Refused2007-10-09
Stockton Wind Turbine
Ecotricity · 07/98/0343/f · 37.8 mo to decide
1.5Application Refused2001-05-02
Brundish Wind Turbine
Western Windpower / Ecotricity · 07/98/0342/F · 37.8 mo to decide
1.5Application Refused2001-05-02

Does South Norfolk approve onshore wind schemes?

Yes — of the 6 onshore wind schemes South Norfolk has decided, 0% were approved (0 granted, 6 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in South Norfolk?

The median time from application to decision is 9.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has South Norfolk consented?

0 MW has been consented across 0 approved schemes, with 48 MW refused. A further 1 application awaits a decision.

Other technologies in South Norfolk

Solar in South NorfolkBattery storage in South Norfolk

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.