Novarly ParcelRenewable planning

Renewable planning Onshore windPeterborough

Onshore wind planning in Peterborough

Peterborough has decided 4 onshore wind schemes and approved 50% of them, taking a median of 31.7 months to decide. Consented capacity: 30 MW. 1 application still awaiting a decision.

50%
Approved
2 granted · 2 refused
31.7 mo
Median decision
UK 11.5 mo
30 MW
Consented
24 MW refused
4
Appeals
3 allowed on appeal

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Peterborough compares

Against the 75 UK authorities with 5+ onshore wind decisions, Peterborough sits in the 20th percentile for approval rate (18 points below the England average) and the 4th percentile for speed.

Decisions by year

35Approved — 2 (2010)210Refused — 1 (2014)114
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Willow Hall Farm
REG Windpower · 14/01136/FUL
10Application Withdrawn2015-11-11
Gores Wind Farm
Peterborough Wind Energy · 13/00431/FUL
16Application Withdrawn2015-10-28
Hundred Road Wind Turbines
FCC Environment · F/YR11/0444/F · 41.2 mo to decide
6Appeal Withdrawn2014-11-13
French Farm 2 (Extension)
REG Windpower · 13/00933/FUL · 7.3 mo to decide
8Application Refused2014-02-06
French Farm
REG Windpower (previously Cornwall Light and Power) · 08/01365/FUL · 22.1 mo to decide
4Operational2010-09-10
Wryde Croft
Renewable Energy Systems (RES) · 07/01411/FUL · 45 mo to decide
26Operational2010-04-01
Nutsgrove Wind Farm
WPR Wind Ltd · 06/01051/FUL · 44.8 mo to decide
14.4Abandoned2010-04-01
French Farm
Cornwall Light and Power · 04/00902/FUL
4Revised2008-12-10
Morris Fen (Wind)
Wind Prospect · 03/01247/FUL · 7.6 mo to decide
16Application Refused2004-04-23

Does Peterborough approve onshore wind schemes?

Yes — of the 4 onshore wind schemes Peterborough has decided, 50% were approved (2 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Peterborough?

The median time from application to decision is 31.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Peterborough consented?

30 MW has been consented across 2 approved schemes, with 24 MW refused. A further 1 application awaits a decision.

Other technologies in Peterborough

Solar in PeterboroughBattery storage in Peterborough

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com