Renewable planning › Onshore wind › Middlesbrough
Onshore wind planning in Middlesbrough
Middlesbrough has decided 1 onshore wind scheme and approved 100% of them, taking a median of 1.7 months to decide. Consented capacity: 2 MW.
⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Middlesbrough compares
Against the 75 UK authorities with 5+ onshore wind decisions, Middlesbrough sits in the 98th percentile for approval rate (32 points above the England average) and the 100th percentile for speed.
Every recorded scheme (1)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Riverside Stadium Empowering Wind · M/FP/0849/08/P · 1.7 mo to decide | 1.5 | Planning Permission Expired | 2008-07-07 |
Does Middlesbrough approve onshore wind schemes?
Yes — of the 1 onshore wind schemes Middlesbrough has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in Middlesbrough?
The median time from application to decision is 1.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Middlesbrough consented?
2 MW has been consented across 1 approved scheme. There are no applications currently awaiting a decision.
Other technologies in Middlesbrough
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report