Novarly ParcelRenewable planning

Renewable planning Onshore windEast Suffolk

Onshore wind planning in East Suffolk

East Suffolk has decided 6 onshore wind schemes and approved 67% of them, taking a median of 5.4 months to decide. Consented capacity: 20 MW. 4 applications still awaiting a decision.

67%
Approved
4 granted · 2 refused
5.4 mo
Median decision
UK 11.5 mo
20 MW
Consented
18 MW refused
2
Appeals
2 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How East Suffolk compares

Against the 75 UK authorities with 5+ onshore wind decisions, East Suffolk sits in the 45th percentile for approval rate (1 points below the England average) and the 95th percentile for speed.

Decisions by year

35Refused — 2 (2010)210Approved — 1 (2013)113Approved — 1 (2014)114
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Laurels Farm
Stamford Renewable Power · DC/12/1332/FUL · 16.1 mo to decide
2Planning Permission Expired2014-04-02
Upper Holton Wind Farm
Temporis Capital · DC/13/0014/DRC · 1.2 mo to decide
11.5Operational2013-02-12
Granary farm
Brian Barker · DC/10/0910/FUL · 3.6 mo to decide
9Application Refused2010-10-25
Devonshire Farm
Unknown · DC/10/0909/FUL · 3.6 mo to decide
9Application Refused2010-10-25
Laurels Farm
Stamford Renewables · DC/10/0908/FUL · 3.6 mo to decide
9Revised2010-10-25
Devonshire Farm
SRL · DC/10/0048/FUL
9Revised2010-06-18
Granary farm
Stamford Renewables · DC/10/0088/FUL
9Revised2010-06-18
Laurels Farm
Stamford Renewables · DC/10/0091/FUL
9Revised2010-06-18
Bernard Matthews Wind Farm
Bernard Matthews · DC/09/0491/FUL
11.5Application Withdrawn2010-02-17
Wind Farm Africa Alive
SLP Energy · DC/06/1401/FUL · 16.4 mo to decide
4.1Operational2008-05-01
Parham Airfield (wind)
Your Energy · C05/0400 · 7.2 mo to decide
13.8Abandoned2005-10-05
Ness point Wind Turbine 1
SLP Energy · W14512/1 · 10.9 mo to decide
2.3Operational2002-09-27

Does East Suffolk approve onshore wind schemes?

Yes — of the 6 onshore wind schemes East Suffolk has decided, 67% were approved (4 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in East Suffolk?

The median time from application to decision is 5.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has East Suffolk consented?

20 MW has been consented across 4 approved schemes, with 18 MW refused. A further 4 applications awaits a decision.

Other technologies in East Suffolk

Solar in East SuffolkBattery storage in East Suffolk

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com