Onshore wind planning in Dorset

Dorset has decided 5 onshore wind schemes and approved 20% of them, taking a median of 14.4 months to decide. Consented capacity: 9 MW. 4 applications still awaiting a decision.

20%
Approved
1 granted · 4 refused
14.4 mo
Median decision
UK 11.5 mo
9 MW
Consented
65 MW refused
2
Appeals
1 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Dorset compares

Against the 75 UK authorities with 5+ onshore wind decisions, Dorset sits in the 3rd percentile for approval rate (48 points below the England average) and the 51st percentile for speed.

Decisions by year

35Refused — 1 (2011)111Approved — 1 (2012)112Refused — 1 (2015)115Refused — 1 (2016)116
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Rogers Hill Farm -Wind Turbine Repowering
Distributed Generation Limited · P/FUL/2025/01365
2Application Submitted2025-03-20
Slyer's Lane
Broadview Energy · WD/D/14/002611 · 14.4 mo to decide
18Application Refused2016-01-29
West Dorset Wind Farm
West Dorset Wind Energy · WD/D/14/000885
12.5Application Withdrawn2015-10-23
Blandford Hill Wind Farm
REG Windpower · 2/2014/0768/PAEIA · 8.6 mo to decide
12Application Refused2015-03-17
West Dorset Wind Farm
West Coast Energy · 1/D/13/000183
12.5Revised2013-10-24
Alaska Wind Farm
Alaska (formerly Purbeck Wind Farm LLP c/o Infinergy) · 6/2010/0082 · 31.5 mo to decide
9.2Awaiting Construction2012-07-06
Silton Wind Farm
Ecotricity / Next Generation · 2/2010/0731/PLNG · 6.9 mo to decide
10Appeal Refused2011-03-01
Silton Wind Park
Ecotricity / Next Generation · 2/2008/0661
8Revised2009-07-12
Brackenbury Infant School
Brackenbury Infant School
2.5Application Withdrawn2009-02-04
Alaska Wind Farm
Infinergy · 6/2008/0234
13.8Revised2008-12-17
Part Bushes Farm
Lower Winterbourne Wind Farm Ltd · 2-2003-0765 · 14.8 mo to decide
24.8Application Refused2004-10-26

Does Dorset approve onshore wind schemes?

Yes — of the 5 onshore wind schemes Dorset has decided, 20% were approved (1 granted, 4 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Dorset?

The median time from application to decision is 14.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Dorset consented?

9 MW has been consented across 1 approved scheme, with 65 MW refused. A further 4 applications awaits a decision.

Other technologies in Dorset

Solar in DorsetBattery storage in Dorset

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.