Onshore wind planning in Bolton

Bolton has decided 1 onshore wind scheme and approved 0% of them, taking a median of 4.5 months to decide.

0%
Approved
0 granted · 1 refused
4.5 mo
Median decision
UK 11.5 mo
0 MW
Consented
5 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Bolton compares

Against the 75 UK authorities with 5+ onshore wind decisions, Bolton sits in the 0th percentile for approval rate (68 points below the England average) and the 97th percentile for speed.

Every recorded scheme (1)

SchemeMWStatusDecided
Chadwick Wind Turbines
Private Developer · 87494/12 · 4.5 mo to decide
4.5Application Refused2012-06-22

Does Bolton approve onshore wind schemes?

Yes — of the 1 onshore wind schemes Bolton has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Bolton?

The median time from application to decision is 4.5 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Bolton consented?

0 MW has been consented across 0 approved schemes, with 5 MW refused. There are no applications currently awaiting a decision.

Other technologies in Bolton

Solar in BoltonBattery storage in Bolton

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.