Battery storage planning in Warrington
Warrington has decided 4 battery storage schemes and approved 75% of them, taking a median of 5 months to decide. Consented capacity: 150 MW.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Warrington compares
Against the 137 UK authorities with 5+ battery storage decisions, Warrington sits in the 7th percentile for approval rate (17 points below the England average) and the 62nd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (4)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Station Road, Fiddlers Ferry - Battery Energy Storage Net Zero One Limited · 2025/00999/FULM · 4.6 mo to decide | 250 | Application Refused | 2025-12-04 |
Grappenhall Village Sports Club, Stockton Lane - Energy Storage System AMP Clean Energy · 2025/00557/FUL · 1.4 mo to decide | 0.2 | Awaiting Construction | 2025-07-17 |
Biffa Waste Services, Manchester Road - Battery Storage Biffa Waste Services · 2023/00152/FUL · 5.5 mo to decide | — | Awaiting Construction | 2023-09-04 |
Fiddlers Ferry Power Station - Battery storage SSE Enterprise (SSE PLC) · 2022/41800 · 10.8 mo to decide | 150 | Under Construction | 2023-06-20 |
Does Warrington approve battery storage schemes?
Yes — of the 4 battery storage schemes Warrington has decided, 75% were approved (3 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Warrington?
The median time from application to decision is 5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Warrington consented?
150 MW has been consented across 3 approved schemes, with 250 MW refused. There are no applications currently awaiting a decision.
Other technologies in Warrington
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.