Battery storage planning in Vale of Glamorgan

Vale of Glamorgan has decided 3 battery storage schemes and approved 67% of them, taking a median of 6.2 months to decide. Consented capacity: 50 MW. 2 applications still awaiting a decision.

67%
Approved
2 granted · 1 refused
6.2 mo
Median decision
UK 6 mo
50 MW
Consented
50 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Vale of Glamorgan compares

Against the 137 UK authorities with 5+ battery storage decisions, Vale of Glamorgan sits in the 4th percentile for approval rate (25 points below the England average) and the 43rd percentile for speed.

Decisions by year

35Approved — 1 (2025)Refused — 1 (2025)225Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Sully Moors Road - Battery Energy Storage Facility
Centrica Plc Head Office · 2025/00807/FUL · 6.2 mo to decide
50Awaiting Construction2026-02-13
Aberthaw Battery Energy Storage System
Aberthaw Energy Limited · 2025/01282/FUL
249Application Submitted2025-12-16
Castle Road, Burton - Battery Energy Storage System
Rewe 7 Limited · 2025/00525/FUL
440Application Submitted2025-05-29
Pen Y Maes, Ashby Road - Battery Energy Storage
Root Power South Limited · 2024/00999/FUL · 6.9 mo to decide
50Application Refused2025-05-23
Old Wallace Farm, Dyffryn - Battery Energy Storage
Green Field Energy Developments Limited · 2024/01212/FUL · 5.4 mo to decide
Awaiting Construction2025-05-16

Does Vale of Glamorgan approve battery storage schemes?

Yes — of the 3 battery storage schemes Vale of Glamorgan has decided, 67% were approved (2 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Vale of Glamorgan?

The median time from application to decision is 6.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Vale of Glamorgan consented?

50 MW has been consented across 2 approved schemes, with 50 MW refused. A further 2 applications awaits a decision.

Other technologies in Vale of Glamorgan

Solar in Vale of GlamorganOnshore wind in Vale of Glamorgan

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com