Battery storage planning in Stroud
Stroud has decided 4 battery storage schemes and approved 75% of them, taking a median of 11.9 months to decide. Consented capacity: 86 MW. 4 applications still awaiting a decision.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Stroud compares
Against the 137 UK authorities with 5+ battery storage decisions, Stroud sits in the 7th percentile for approval rate (17 points below the England average) and the 9th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (10)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Kingston Road, Slimbridge - Battery Storage Relay Slimbridge Limited · S.23/1593/FUL · 10.4 mo to decide | 36 | Awaiting Construction | 2024-07-17 |
Hook Street - Energy Storage Compound Immersa · S.21/3064/FUL · 18.1 mo to decide | 100 | Application Refused | 2023-06-29 |
Arlingham Solar Farm - Solar PV Panels & Battery Storage Facility Kronos Solar · S.22/1371/FUL | 49.9 | Application Withdrawn | 2022-12-15 |
Woodlands Farm, Clapton - Ground Mounted Solar Park Ecotricity Generation Limited · S.22/1955/FUL | — | Application Submitted | 2022-10-24 |
Gloucestershire Science And Technology Par - Energy Storage Facility Ecotricity Berkeley Storage Limited · S.22/0352/FUL · 7.4 mo to decide | — | Awaiting Construction | 2022-10-05 |
Kingston Road, Slimbridge - Battery Storage Relay Slimbridge Limited · S.22/1157/FUL | 36 | Revised | 2022-06-13 |
Moreton Lane - Solar Farm & Battery Storage JBM Solar Projects 7 Limited · S.21/0465/FUL · 13.3 mo to decide | 49.9 | Awaiting Construction | 2022-04-05 |
Land North of Actrees Solar Farm Immersa · S.19/0372/FUL | 49.9 | Abandoned | 2019-03-07 |
Gloucestershire Science and Technology Park Ecotricity · S.18/0019/FUL | 30 | Revised | 2018-01-03 |
Gloucestershire Science and Technology Park (small) Ecotricity · S.17/2430/FUL | 32 | Revised | 2017-10-25 |
Does Stroud approve battery storage schemes?
Yes — of the 4 battery storage schemes Stroud has decided, 75% were approved (3 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Stroud?
The median time from application to decision is 11.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Stroud consented?
86 MW has been consented across 3 approved schemes, with 100 MW refused. A further 4 applications awaits a decision.
Other technologies in Stroud
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.