Battery storage planning in Stroud

Stroud has decided 4 battery storage schemes and approved 75% of them, taking a median of 11.9 months to decide. Consented capacity: 86 MW. 4 applications still awaiting a decision.

75%
Approved
3 granted · 1 refused
11.9 mo
Median decision
UK 6 mo
86 MW
Consented
100 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Stroud compares

Against the 137 UK authorities with 5+ battery storage decisions, Stroud sits in the 7th percentile for approval rate (17 points below the England average) and the 9th percentile for speed.

Decisions by year

35Approved — 2 (2022)222Refused — 1 (2023)123Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (10)

SchemeMWStatusDecided
Kingston Road, Slimbridge - Battery Storage
Relay Slimbridge Limited · S.23/1593/FUL · 10.4 mo to decide
36Awaiting Construction2024-07-17
Hook Street - Energy Storage Compound
Immersa · S.21/3064/FUL · 18.1 mo to decide
100Application Refused2023-06-29
Arlingham Solar Farm - Solar PV Panels & Battery Storage Facility
Kronos Solar · S.22/1371/FUL
49.9Application Withdrawn2022-12-15
Woodlands Farm, Clapton - Ground Mounted Solar Park
Ecotricity Generation Limited · S.22/1955/FUL
Application Submitted2022-10-24
Gloucestershire Science And Technology Par - Energy Storage Facility
Ecotricity Berkeley Storage Limited · S.22/0352/FUL · 7.4 mo to decide
Awaiting Construction2022-10-05
Kingston Road, Slimbridge - Battery Storage
Relay Slimbridge Limited · S.22/1157/FUL
36Revised2022-06-13
Moreton Lane - Solar Farm & Battery Storage
JBM Solar Projects 7 Limited · S.21/0465/FUL · 13.3 mo to decide
49.9Awaiting Construction2022-04-05
Land North of Actrees Solar Farm
Immersa · S.19/0372/FUL
49.9Abandoned2019-03-07
Gloucestershire Science and Technology Park
Ecotricity · S.18/0019/FUL
30Revised2018-01-03
Gloucestershire Science and Technology Park (small)
Ecotricity · S.17/2430/FUL
32Revised2017-10-25

Does Stroud approve battery storage schemes?

Yes — of the 4 battery storage schemes Stroud has decided, 75% were approved (3 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Stroud?

The median time from application to decision is 11.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Stroud consented?

86 MW has been consented across 3 approved schemes, with 100 MW refused. A further 4 applications awaits a decision.

Other technologies in Stroud

Solar in StroudOnshore wind in Stroud

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.