Battery storage planning in Stafford

Stafford has decided 4 battery storage schemes and approved 100% of them, taking a median of 9.7 months to decide. Consented capacity: 40 MW. 3 applications still awaiting a decision.

100%
Approved
4 granted · 0 refused
9.7 mo
Median decision
UK 6 mo
40 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Stafford compares

Against the 137 UK authorities with 5+ battery storage decisions, Stafford sits in the 73rd percentile for approval rate (8 points above the England average) and the 12th percentile for speed.

Decisions by year

35Approved — 1 (2022)122Approved — 1 (2023)123Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Brooms Road - Micro Energy Storage
AMP Clean Energy · 25/41276/FUL
0.2Application Submitted2025-10-10
Yew Tree Farm, Drointon Lane
Push Energy · 25/40571/FUL
30Application Submitted2025-05-07
Lower Farm, Drointon Lane - Solar farm & Battery Energy Storage
Innova Renewables · 23/36938/FUL · 22 mo to decide
30Awaiting Construction2025-01-14
Grey Friars Way - Battery Storage
Mercia Power Response · 23/37405/FUL · 9.7 mo to decide
Awaiting Construction2024-03-04
Flashbrook Road, Knighton - Solar Farm
Scottish Power Renewables · 22/36478/FUL
15Application Submitted2024-02-29
Aspley House Farm, Aspley Lane - Battery Storage Facility
Hydrock · 22/36378/FUL · 3.5 mo to decide
10Awaiting Construction2023-01-27
Barlaston - Battery Energy Storage System
Dorrymee Limited · 21/35342/FUL · 9.8 mo to decide
Awaiting Construction2022-10-03

Does Stafford approve battery storage schemes?

Yes — of the 4 battery storage schemes Stafford has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Stafford?

The median time from application to decision is 9.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Stafford consented?

40 MW has been consented across 4 approved schemes. A further 3 applications awaits a decision.

Other technologies in Stafford

Solar in StaffordOnshore wind in Stafford

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.