Battery storage planning in Slough

Slough has decided 1 battery storage scheme and approved 0% of them, taking a median of 5.3 months to decide. 1 application still awaiting a decision.

0%
Approved
0 granted · 1 refused
5.3 mo
Median decision
UK 6 mo
0 MW
Consented
2 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Slough compares

Against the 137 UK authorities with 5+ battery storage decisions, Slough sits in the 0th percentile for approval rate (92 points below the England average) and the 57th percentile for speed.

Every recorded scheme (2)

SchemeMWStatusDecided
Manor Farm, Poyle Road - Battery Energy Storage
Private Developer · P/10076/013
Application Submitted2025-01-02
Galleymead House, Old Bath Road - Battery Storage
Power & Energy Fields Limited · P/10697/017 · 5.3 mo to decide
2Application Refused2024-03-11

Does Slough approve battery storage schemes?

Yes — of the 1 battery storage schemes Slough has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Slough?

The median time from application to decision is 5.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Slough consented?

0 MW has been consented across 0 approved schemes, with 2 MW refused. A further 1 application awaits a decision.

Other technologies in Slough

Solar in SloughOnshore wind in Slough

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.