Renewable planning › Battery storage › Shetland Islands
Battery storage planning in Shetland Islands
Shetland Islands has decided 3 battery storage schemes and approved 100% of them, taking a median of 14.8 months to decide. Consented capacity: 16 MW.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Shetland Islands compares
Against the 137 UK authorities with 5+ battery storage decisions, Shetland Islands sits in the 73rd percentile for approval rate (8 points above the England average) and the 4th percentile for speed.
Every recorded scheme (4)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Luggies Knowe, Hill Of Gremista - Wind Turbines & Battery Storage Shetland Aerogenerators Ltd · 2024/006/PPF · 14.8 mo to decide | 14.9 | Awaiting Construction | 2025-04-18 |
Gremista Greener Grid Park Stabilisation Facility Statkraft Wind UK Limited · 2023/033/PPF | — | Application Withdrawn | 2023-06-27 |
Foula Community Electricity Scheme Foula Community Electricity Trust | — | Operational | 2009-12-24 |
Northern Isles New Energy Solution (NINES) 1 Scottish Hydroelectric Power Distribution (SHEPD) | 1 | Operational | — |
Does Shetland Islands approve battery storage schemes?
Yes — of the 3 battery storage schemes Shetland Islands has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Shetland Islands?
The median time from application to decision is 14.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Shetland Islands consented?
16 MW has been consented across 3 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Shetland Islands
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.