Battery storage planning in Shetland Islands

Shetland Islands has decided 3 battery storage schemes and approved 100% of them, taking a median of 14.8 months to decide. Consented capacity: 16 MW.

100%
Approved
3 granted · 0 refused
14.8 mo
Median decision
UK 6 mo
16 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Shetland Islands compares

Against the 137 UK authorities with 5+ battery storage decisions, Shetland Islands sits in the 73rd percentile for approval rate (8 points above the England average) and the 4th percentile for speed.

Every recorded scheme (4)

SchemeMWStatusDecided
Luggies Knowe, Hill Of Gremista - Wind Turbines & Battery Storage
Shetland Aerogenerators Ltd · 2024/006/PPF · 14.8 mo to decide
14.9Awaiting Construction2025-04-18
Gremista Greener Grid Park Stabilisation Facility
Statkraft Wind UK Limited · 2023/033/PPF
Application Withdrawn2023-06-27
Foula Community Electricity Scheme
Foula Community Electricity Trust
Operational2009-12-24
Northern Isles New Energy Solution (NINES) 1
Scottish Hydroelectric Power Distribution (SHEPD)
1Operational

Does Shetland Islands approve battery storage schemes?

Yes — of the 3 battery storage schemes Shetland Islands has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Shetland Islands?

The median time from application to decision is 14.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Shetland Islands consented?

16 MW has been consented across 3 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Shetland Islands

Solar in Shetland IslandsOnshore wind in Shetland Islands

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report