Battery storage planning in Reigate and Banstead

Reigate and Banstead has decided 3 battery storage schemes and approved 100% of them, taking a median of 5 months to decide. 1 application still awaiting a decision.

100%
Approved
3 granted · 0 refused
5 mo
Median decision
UK 6 mo
0 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Reigate and Banstead compares

Against the 137 UK authorities with 5+ battery storage decisions, Reigate and Banstead sits in the 73rd percentile for approval rate (8 points above the England average) and the 62nd percentile for speed.

Decisions by year

35Approved — 1 (2021)121Approved — 1 (2023)123Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Surrey Fire And Rescue Headquarters, Wray Park Road - Battery Storage
AMP Clean Energy · 24/01421/F
0.2Application Withdrawn2024-11-28
Woodhatch Place, Cockshot Hill - Micro Energy Storage System
AMP Energy Services Limited · 24/01422/F · 2.7 mo to decide
0.2Awaiting Construction2024-10-24
Merstham Community Hub, Merstham - Energy Storage Facility
Aggregated Micro Power Holdings Plc · 24/01420/F
0.2Application Submitted2024-07-31
Duxhurst Farm, Duxhurst Lane - Solar Farm
Luminous Energy Limited · 22/02783/F · 11.3 mo to decide
Awaiting Construction2023-12-15
South Terminal Car Park Forecourt - Electric Vehicle Charging Forecourt
Gatwick Airport Limited · CR/2021/0066/CON · 5 mo to decide
Under Construction2021-06-29

Does Reigate and Banstead approve battery storage schemes?

Yes — of the 3 battery storage schemes Reigate and Banstead has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Reigate and Banstead?

The median time from application to decision is 5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Reigate and Banstead consented?

0 MW has been consented across 3 approved schemes. A further 1 application awaits a decision.

Other technologies in Reigate and Banstead

Solar in Reigate and BansteadOnshore wind in Reigate and Banstead

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.