Novarly ParcelRenewable planning

Renewable planning Battery storageRedditch

Battery storage planning in Redditch

Redditch has decided 2 battery storage schemes and approved 100% of them, taking a median of 7.6 months to decide. 3 applications still awaiting a decision.

100%
Approved
2 granted · 0 refused
7.6 mo
Median decision
UK 6 mo
0 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Redditch compares

Against the 137 UK authorities with 5+ battery storage decisions, Redditch sits in the 73rd percentile for approval rate (8 points above the England average) and the 26th percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 1 (2022)122
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (6)

SchemeMWStatusDecided
Wheaten Hill Farm - BESS
Boom Power Limited · 25/00888/FUL
400Application Submitted2025-08-06
Feckenham Energy Storage System
Anesco Limited · 25/00628/FUL
Application Submitted2025-05-27
Astwood Lane, Feckenham - Battery Storage
Immersa Limited · 23/00417/FUL
200Application Submitted2023-03-31
Astwood Lane - Greener Grid Park & Energy Storage
Statkraft Wind UK Limited · 21/00195/FUL · 12 mo to decide
Awaiting Construction2022-01-21
Woolaston Road
Mercia Power Response · 20/01011/FUL · 3.3 mo to decide
Awaiting Construction2020-12-03
Feckenham Energy Storage System
Anesco · 17/00453/FUL
18Application Withdrawn2017-11-13

Does Redditch approve battery storage schemes?

Yes — of the 2 battery storage schemes Redditch has decided, 100% were approved (2 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Redditch?

The median time from application to decision is 7.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Redditch consented?

0 MW has been consented across 2 approved schemes. A further 3 applications awaits a decision.

Other technologies in Redditch

Solar in RedditchOnshore wind in Redditch

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report