Novarly ParcelRenewable planning

Renewable planning Battery storagePortsmouth

Battery storage planning in Portsmouth

Portsmouth has decided 2 battery storage schemes and approved 100% of them, taking a median of 3.6 months to decide. Consented capacity: 2 MW. 1 application still awaiting a decision.

100%
Approved
2 granted · 0 refused
3.6 mo
Median decision
UK 6 mo
2 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Portsmouth compares

Against the 137 UK authorities with 5+ battery storage decisions, Portsmouth sits in the 73rd percentile for approval rate (8 points above the England average) and the 77th percentile for speed.

Every recorded scheme (3)

SchemeMWStatusDecided
Fort Widley, Portsdown Hill Road - Battery Energy Storage System
Voltwise Power Holdings Limited · 25/00797/FUL
120Application Submitted2025-07-31
St James Hospital Solent Nhs Trust, Locksway Road - Energy Centre
Solent NHS Trust · 22/01343/FUL · 2.5 mo to decide
Awaiting Construction2022-12-06
Lakeside Business Park
Custom Solar Limited · 22/00487/FUL · 4.7 mo to decide
2Under Construction2022-11-01

Does Portsmouth approve battery storage schemes?

Yes — of the 2 battery storage schemes Portsmouth has decided, 100% were approved (2 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Portsmouth?

The median time from application to decision is 3.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Portsmouth consented?

2 MW has been consented across 2 approved schemes. A further 1 application awaits a decision.

Other technologies in Portsmouth

Solar in PortsmouthOnshore wind in Portsmouth

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report