Renewable planning Battery storageEastleigh

Battery storage planning in Eastleigh

Eastleigh has decided 2 battery storage schemes and approved 100% of them, taking a median of 7.4 months to decide. Consented capacity: 22 MW. 1 application still awaiting a decision.

100%
Approved
2 granted · 0 refused
7.4 mo
Median decision
UK 6 mo
22 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Eastleigh compares

Against the 137 UK authorities with 5+ battery storage decisions, Eastleigh sits in the 73rd percentile for approval rate (8 points above the England average) and the 28th percentile for speed.

Decisions by year

35Approved — 1 (2019)119Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (3)

SchemeMWStatusDecided
Allington Lane - Solar & Battery Farm
Eastleigh Borough Council · F/23/96527 · 7.2 mo to decide
16Awaiting Construction2024-07-26
Hound Road
Conrad Energy (Developments) Limited · F/20/88834
Application Submitted2020-09-23
Hamble Lane Battery Energy Storage
Balanced Grid Solutions · F/19/85302 · 7.6 mo to decide
6Awaiting Construction2019-11-22

Does Eastleigh approve battery storage schemes?

Yes — of the 2 battery storage schemes Eastleigh has decided, 100% were approved (2 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Eastleigh?

The median time from application to decision is 7.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Eastleigh consented?

22 MW has been consented across 2 approved schemes. A further 1 application awaits a decision.

Other technologies in Eastleigh

Solar in EastleighOnshore wind in Eastleigh

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com