Renewable planning › Battery storage › Darlington
Battery storage planning in Darlington
Darlington has decided 4 battery storage schemes and approved 100% of them, taking a median of 7.8 months to decide. Consented capacity: 43 MW.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Darlington compares
Against the 137 UK authorities with 5+ battery storage decisions, Darlington sits in the 73rd percentile for approval rate (8 points above the England average) and the 26th percentile for speed.
Every recorded scheme (5)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Carlbury - Battery Energy Storage AMP Clean Energy · 25/01371/FUL | 0.2 | Application Withdrawn | 2026-01-09 |
Long Pasture Farm, Little Stainton - Solar Farm Electric Works · 22/01329/FUL · 7.8 mo to decide | 40 | Awaiting Construction | 2023-08-10 |
Rise Carr, Darlington / CLNR EES3-1 Northern Powergrid | 2.5 | Operational | — |
Harrowgate Hill, Darlington / CLNR ESS3-2 Northern Powergrid | 0.1 | Decommissioned | — |
High Northgate, Darlington / CLNR ESS3-3 Northern Powergrid | 0.1 | Decommissioned | — |
Does Darlington approve battery storage schemes?
Yes — of the 4 battery storage schemes Darlington has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Darlington?
The median time from application to decision is 7.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Darlington consented?
43 MW has been consented across 4 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Darlington
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report