Renewable planning Battery storageChorley

Battery storage planning in Chorley

Chorley has decided 3 battery storage schemes and approved 100% of them, taking a median of 3.1 months to decide. Consented capacity: 50 MW. 1 application still awaiting a decision.

100%
Approved
3 granted · 0 refused
3.1 mo
Median decision
UK 6 mo
50 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Chorley compares

Against the 137 UK authorities with 5+ battery storage decisions, Chorley sits in the 73rd percentile for approval rate (8 points above the England average) and the 85th percentile for speed.

Decisions by year

35Approved — 1 (2022)122Approved — 1 (2024)124Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (4)

SchemeMWStatusDecided
Strawberry Fields Business Park, Berry Way - Energy Storage System
AMP Clean Energy · 25/01211/FUL · 2.2 mo to decide
0.2Awaiting Construction2026-02-18
Green Energy Park, Eyes Lane - BESS
GA Pet Food Partners Group Limited · 25/01256/FULMAJ
5Application Submitted2026-01-14
Vause Farm - Battery Storage
Sirius Renewable Energy Limited · 22/00362/FULMAJ · 22.4 mo to decide
20Awaiting Construction2024-02-09
Charnock Richard - Battery Storage
Pulse Clean Energy · 22/00204/FUL · 3.1 mo to decide
30Operational2022-05-27

Does Chorley approve battery storage schemes?

Yes — of the 3 battery storage schemes Chorley has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Chorley?

The median time from application to decision is 3.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Chorley consented?

50 MW has been consented across 3 approved schemes. A further 1 application awaits a decision.

Other technologies in Chorley

Solar in ChorleyOnshore wind in Chorley

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.