Renewable planning › Battery storage › Barnet
Battery storage planning in Barnet
Barnet has decided 1 battery storage scheme and approved 100% of them, taking a median of 29.8 months to decide. Consented capacity: 50 MW.
⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Barnet compares
Against the 137 UK authorities with 5+ battery storage decisions, Barnet sits in the 73rd percentile for approval rate (8 points above the England average) and the -1st percentile for speed.
Every recorded scheme (1)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Mill Hill National Grid Substation Harbour Energy · 20/4241/FUL · 29.8 mo to decide | 49.9 | Awaiting Construction | 2023-03-13 |
Does Barnet approve battery storage schemes?
Yes — of the 1 battery storage schemes Barnet has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Barnet?
The median time from application to decision is 29.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Barnet consented?
50 MW has been consented across 1 approved scheme. There are no applications currently awaiting a decision.
Other technologies in Barnet
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.