Renewable sites › Sanquhar 2 Community Wind Farm
Sanquhar 2 Community Wind Farm
Sanquhar 2 Community Wind Farm is under construction in Scottish Government (S36).
Planning and build timeline
| Application submitted | 2019-03-21 |
| Permission granted | 2023-08-31 53 months after submission |
| Operational | not recorded |
Scottish Government (S36)’s record on battery storage
Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sanquhar 2 Community Wind Farm Wind Onshore · Under Construction | 308 | 0 km |
Sanquhar Community Windfarm Wind Onshore · Operational | 32.4 | 4.4 km |
Whiteside Hill Wind Onshore · Operational | 25.3 | 6.1 km |
Afton Wind Farm Wind Onshore · Operational | 50 | 6.5 km |
Hare Hill Extension Wind Onshore · Operational | 29.8 | 7 km |
Hare Hill (East Ayrshire) Wind Onshore · Operational | 13.2 | 7 km |
Brochloch Rig 1 (formerly Windy Standard) Wind Onshore · Operational | 21.6 | 7.1 km |
Sandy Knowe Wind Farm Wind Onshore · Operational | 81.6 | 7.3 km |
How big is Sanquhar 2 Community Wind Farm?
REPD does not record an installed capacity for Sanquhar 2 Community Wind Farm.
Who operates Sanquhar 2 Community Wind Farm?
REPD records the operator as Community Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sanquhar 2 Community Wind Farm approved and built?
The application was submitted on 2019-03-21. Permission was granted on 2023-08-31, 53 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 14708.