Renewable planning › Onshore wind › West Berkshire
Onshore wind planning in West Berkshire
West Berkshire has decided 2 onshore wind schemes and approved 0% of them, taking a median of 7 months to decide. 1 application still awaiting a decision.
⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How West Berkshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, West Berkshire sits in the 0th percentile for approval rate (68 points below the England average) and the 88th percentile for speed.
Every recorded scheme (3)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Membury Energy4All · 07/01018/FUL · 7 mo to decide | 2 | Application Refused | 2007-12-11 |
Baydon Meadow Unknown · 6.3 mo to decide | 1.3 | Application Refused | 2007-12-11 |
Baydon Meadows Matthew Partridge · 02/02495/FUL · 11.5 mo to decide | 1.3 | Revised | 2003-11-12 |
Does West Berkshire approve onshore wind schemes?
Yes — of the 2 onshore wind schemes West Berkshire has decided, 0% were approved (0 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in West Berkshire?
The median time from application to decision is 7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has West Berkshire consented?
0 MW has been consented across 0 approved schemes, with 3 MW refused. A further 1 application awaits a decision.
Other technologies in West Berkshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.