Onshore wind planning in North Norfolk

North Norfolk has decided 2 onshore wind schemes and approved 0% of them, taking a median of 8 months to decide.

0%
Approved
0 granted · 2 refused
8 mo
Median decision
UK 11.5 mo
0 MW
Consented
10 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How North Norfolk compares

Against the 75 UK authorities with 5+ onshore wind decisions, North Norfolk sits in the 0th percentile for approval rate (68 points below the England average) and the 85th percentile for speed.

Decisions by year

35Refused — 1 (2010)110Refused — 1 (2013)113
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (2)

SchemeMWStatusDecided
Scottow Estate Wind Farm
Airvolution Energy · PF/13/0033 · 3.2 mo to decide
3.6Application Refused2013-04-15
Grove Farm (wind)
Private Developer · PF/09/1060 · 12.9 mo to decide
6.8Application Refused2010-11-25

Does North Norfolk approve onshore wind schemes?

Yes — of the 2 onshore wind schemes North Norfolk has decided, 0% were approved (0 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in North Norfolk?

The median time from application to decision is 8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has North Norfolk consented?

0 MW has been consented across 0 approved schemes, with 10 MW refused. There are no applications currently awaiting a decision.

Other technologies in North Norfolk

Solar in North NorfolkBattery storage in North Norfolk

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.