Novarly ParcelRenewable planning

Renewable planning Onshore windLisburn and Castlereagh

Onshore wind planning in Lisburn and Castlereagh

Lisburn and Castlereagh has decided 2 onshore wind schemes and approved 100% of them, taking a median of 11.2 months to decide. Consented capacity: 1 MW. 1 application still awaiting a decision.

100%
Approved
2 granted · 0 refused
11.2 mo
Median decision
UK 11.5 mo
1 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Lisburn and Castlereagh compares

Against the 75 UK authorities with 5+ onshore wind decisions, Lisburn and Castlereagh sits in the 98th percentile for approval rate (32 points above the England average) and the 68th percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 1 (2021)121
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (4)

SchemeMWStatusDecided
Ballynahinch Road
Arena Capital Partners Limited · LA07/20/1409/F · 10.9 mo to decide
0.25Awaiting Construction2021-09-01
Ballinderry Road
Private Developer · LA05/2019/1212/F · 11.5 mo to decide
0.3Awaiting Construction2020-11-10
Ballinderry Road
Private Developer · LA05/2019/0855/F
0.3Revised2019-09-19
Ballindery Road
Private Developer · LA05/2019/0400/F
0.9Application Withdrawn2019-06-27

Does Lisburn and Castlereagh approve onshore wind schemes?

Yes — of the 2 onshore wind schemes Lisburn and Castlereagh has decided, 100% were approved (2 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Lisburn and Castlereagh?

The median time from application to decision is 11.2 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Lisburn and Castlereagh consented?

1 MW has been consented across 2 approved schemes. A further 1 application awaits a decision.

Other technologies in Lisburn and Castlereagh

Solar in Lisburn and CastlereaghBattery storage in Lisburn and Castlereagh

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report