Renewable planning › Onshore wind › Hartlepool
Onshore wind planning in Hartlepool
Hartlepool has decided 3 onshore wind schemes and approved 100% of them, taking a median of 12 months to decide. Consented capacity: 18 MW. 1 application still awaiting a decision.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Hartlepool compares
Against the 75 UK authorities with 5+ onshore wind decisions, Hartlepool sits in the 98th percentile for approval rate (32 points above the England average) and the 59th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (8)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Nelson Farm, Nelson Farm Lane - Wind Turbine Constantine Wind Energy Limited · H/2024/0206 · 12 mo to decide | 0.23 | Awaiting Construction | 2025-08-01 |
Tofts Road - Single Wind Turbine Melton Wind Limited · H/2025/0157 | 4.26 | Application Submitted | 2025-07-31 |
Graythorp Wind Turbine Seneca Global Energy · H/2014/0252 | 7.5 | Application Withdrawn | 2018-08-30 |
Tofts Road Wind Turbine Seneca Global Energy · H/2014/0254 | 7.5 | Application Withdrawn | 2018-08-30 |
Brenda Road Wind Turbine Seneca Global Energy · H/2014/0253 | 7.5 | Application Withdrawn | 2018-08-30 |
Sheraton Wind Farm (Hartlepool) EDF Energy Renewables · H/2011/0674 | 2 | Abandoned | 2012-01-24 |
Red Gap Moor Wind Farm Capital Dynamics · H/2009/0231 · 22.3 mo to decide | 12.5 | Operational | 2011-03-31 |
High Volts Wind Farm E.ON UK · 10.4 mo to decide | 5.5 | Operational | 2002-03-27 |
Does Hartlepool approve onshore wind schemes?
Yes — of the 3 onshore wind schemes Hartlepool has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in Hartlepool?
The median time from application to decision is 12 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Hartlepool consented?
18 MW has been consented across 3 approved schemes. A further 1 application awaits a decision.
Other technologies in Hartlepool
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.