Onshore wind planning in Gwynedd

Gwynedd has decided 3 onshore wind schemes and approved 33% of them, taking a median of 10.7 months to decide. Consented capacity: 4 MW. 1 application still awaiting a decision.

33%
Approved
1 granted · 2 refused
10.7 mo
Median decision
UK 11.5 mo
4 MW
Consented
29 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Gwynedd compares

Against the 75 UK authorities with 5+ onshore wind decisions, Gwynedd sits in the 6th percentile for approval rate (35 points below the UK average) and the 69th percentile for speed.

Screening a site of your own?

RedlineUK · £39

Gwynedd approves 33% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site£39
Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Every recorded scheme (4)

SchemeMWStatusDecided
Derwin Fawr - Wind Turbines Replacement
Private Developer · C25/0712/34/LL
0.75Application Submitted2025-09-29
Bodelith Isaf Wind Turbines
Pennant Walters · C14/0291/04/LL · 18.3 mo to decide
5Application Refused2015-10-19
Cwmpenanner
Zepher · 0/28528 · 10.7 mo to decide
24.2Application Refused2004-11-26
Braich Ddu
REG Windpower (previously Cornwall Light and Power) · C04M/0038/04/MW · 6.1 mo to decide
3.9Operational2004-09-13

Does Gwynedd approve onshore wind schemes?

Yes — of the 3 onshore wind schemes Gwynedd has decided, 33% were approved (1 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Gwynedd?

The median time from application to decision is 10.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Gwynedd consented?

4 MW has been consented across 1 approved scheme, with 29 MW refused. A further 1 application awaits a decision.

Other technologies in Gwynedd

Solar in GwyneddBattery storage in Gwynedd

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.